The city of Peru Public Services Committee met Sept. 12 to provide updates on the Venture Drive project.

Here are the meeting's minutes, as provided by the committee:

PUBLIC SERVICES COMMITTEE MEETING MINUTES

DATE OF MEETING: Monday, September 12, 2016 TIME: 10:00 AM

PLACE OF MEETING: Peru Municipal Building

1901 4th Street, Peru, IL 61354

COMMITTEE MEMBERS PRESENT: Chairman Alderman Waldorf, Alderman Jim Lukosus,

Alderman Mike Sapienza. ABSENT: Mayor Scott Harl and Alderman Becky Mueller.

OTHER PERSONS PRESENT: Alderman Tom Payton, Alderman Dave Potthoff, City Clerk

Dave Bartley, PSM Jeff King, City Engineer Eric Carls, ASM Doug Bernabei, City Finance

Officer Justin Miller, Electric Department Clay Huettemann, Economic Development Director

Bob Vickrey, Code Enforcement Officer Josh Theisinger, Chris Perra and Don Kowalczyk of

T.E.S.T., Mike Perry of Chamlin & Associates, and Roger Swenson and Herbert Kuryliw of

NIU.

MINUTES

Alderman Lukosus made a motion to approve the minutes of the August 15, 2016 Public

Services Committee Meeting. Alderman Sapienza seconded the motion; motion carried.

PRESENTATION

Roger Swenson, Network Solutions Architect, and Herbert Kuryliw, Chief Netwoek &

Technology Architect, from Northern Illinois University provided a presentation regarding

IFiber. IFiber has a current relationship with the City and has hardware housed here. They

suggested a partnership approach and to work with Internet Service Providers.

PUBLIC COMMENT

None

WATER & SEWER

City Engineer Eric Carls discussed ongoing improvements that have been taking place at the

water treatment plants; two of the four high service pumps need to be upgraded, but we need to

look at the network as a whole. Chris Perra added these pumps are a major part of the system.

The four pumps are approximately 30 years old and are difficult to have spare parts for. A study

was done in 2004 and needs to be updated. He believes if we have all four pumps identical they

will be able to have spare parts available. Back-up power was also discussed for cases of

catastrophes; groundwater would be able to be used if power was available. Chairman Waldorf

asked if there was a number not to exceed for the service agreement. City Engineer Carls

explained he is working on it and the item can be added to the agenda for the Council meeting

for discussion.

City Engineer Eric Carls reported on discussions that have taken place regarding the options for

the trunk sewer for Arby’s lift station. He stated he wanted to open the discussion and start

looking at costs and permitting; there may be some billings for outside consultation.

T.E.S.T.

ASM Doug Bernabei asked about the ground storage tank work. City Engineer Eric Carls and

Chris Perra of T.E.S.T. reported the contractor has mobilized; work will begin inside and then

move to the outside of the tank. It is unsure the timeline and when it will be complete.

STREETS & ALLEY

None

ELECTRIC

None

LANDFILL

None

AIRPORT

City Clerk Dave Bartley prompted a discussion about cash farm rents. He explained he

corresponded with Ed Keifer from Hertz Farm Management; there are challenges and it would be

best to set it up for next year. There was a consensus to re-visit the item in June.

CEMETERY

None

PARKS & RECREATION

City Engineer Eric Carls reported about correspondence from NCICG to set up a checking

account for funds from the OSLAD grant. A resolution will be added to the next Council

agenda.

PSM Jeff King reported that tennis courts are being repainted today.

CODE ENFORCEMENT/ BUILDING & ZONING

None

ENGINEERING

City Engineer Eric Carls provided updates on the following current projects:

· Area 3 Phase 1 – boring under Rt. 6 will be taking place this week, project is on track and

set for completion in late fall.

· Venture Drive – project is near completion. To be completed it will need the final

surface, signage, and some small landscaping.

· Public Works Building – office work is a little behind, but all else is moving forward.

The rest of the building is full accessible and the moving process has begun. ASM

Bernabei added they are organizing their inventory and establishing a process for

maintaining inventory for the Public Works department. He has gotten input from

Finance Officer Justin Miller and plan to coordinate with the Electric Department.

· Plank Road – awaiting Omni Trax final approval. Hoping for a start date right after

Labor Day.

City Engineer Carls also provided updates on planning for future projects:

· He plans to have the 2017 General Fund Street Program and 2017 MFT projects prepared

by winter.

· There are areas in town that are not part of the long-term sewer separation projects that

have had aging water mains and he is working on a plan for those areas.

· The design work for St. John’s subdivision storm sewer has begun. The project will be

phased over a few construction seasons.

BUILDINGS & GROUNDS

ASM Doug Bernabei reported the planters throughout town will be replaced with mums for fall.

OLD BUSINESS

PSM Jeff King informed that a sewer line has collapsed on Plum St. He is not able to get in to

look right now because it is too wet. Chairman Waldorf suggested using a camera to get a better

look because of past issues in that area.

NEW BUSINESS

City Clerk Dave Bartley initiated a discussion about hosting an electronic recycling event;

options and budget were discussed. Clerk Bartley stated there is a strong demand for one. PSM

Jeff King confirmed this by saying people are dumping t.v.’s around town. Different options

were discussed to cut costs, including charging people. This item will be discussed at committee

of a whole.

City Clerk Dave Bartley also discussed the replacement of a handheld meter reader device. One

was replaced almost two years ago and is still working great. The cost is around $8,000.

Chairman Waldorf asked if it is a necessity. Clerk Bartley responded, yes, and the old handheld

would be an added benefit for the water department. This item will be added to the agenda for

the next City Council meeting.

Alderman Sapienza informed rocks have been coming down on Rock St. PSM Jeff King added

it is the hill between 3rd and 4th St.; adding blacktop will hold the rock back.

PUBLIC COMMENT

None

CLOSED SESSION

None

ADJOURNMENT

Alderman Lukosus made a motion that the meeting be adjourned. Chairman Waldorf seconded

the motion. Meeting adjourned at 11:16 a.m.